Projects Approved
 
Stake Holder - Mysore City Corporation - MCC
  1. Project Implementation Unit
    Appr cost Rs. in Crores - 0.62

     
    • Public Health Engineer, Information Technology Officer and Human Resource Development officer have reported. Tender has been called for the remaining posts.

Pending at GoI

  1. Conservation on Natural lakes in Mysore-Packages 1 (4No. of Lakes - Dalvoy, Hebbal, Bogadi, Ligambudi Lakes)
    Appr cost Rs. in Crores - 6.63
     
    • DPR submitted to GoI for approval. Central Water Commission to scrutiny the DPR.
       
  2. Conservation on Natural lakes in Mysore-Package 2 (4 No. of Lakes - Kukkarahalli, Hinkal, Kyathamanahalli, Devanoor Lakes)
    Appr cost Rs. in Crores - 6.46
     
    • DPR submitted to GoI for approval. Central Water Commission to scrutiny the DPR.
       
  3. Setting up of new Modern Abattoirs
    Appr cost Rs. in Crores - 26.63
     
    • The GOI has been requested to consider this project as an activity under SWM as it is not possible to consider under NABARD as MCC is an Urban area. The matter is under examination of GOI
 
Stake Holder - Karnataka Urban Water Supply - KUWS & D Board
  1. Remodeling of Water Supply distribution network, automation of system and providing integrated management system for Mysore city
    Appr cost Rs. in Crores - 194.54
     
  2. Augmentation of bulk water supply from river Kabini
    Appr cost Rs. in Crores - 108.82
     
    • Process for acquiring 30 acres of land is initiated. Tender document are being prepared.
       
  3. Remodeling of Storm Water Drain in Mysore (104.67km)
    Appr cost Rs. in Crores - 347.28
     
    • The Project has been cleared in CSMC meeting held on 19/12/08. Privatization of valleys is in progress.

Pending at GoI

  1. Remodeling of the UGD network in old areas of the city and development of sewage treatment plant ( STP ) for the uncovered areas
    Appr cost Rs. in Crores - 392.58
     
    • DPR submitted to GOI. Awaiting approval from GoI.
 
Stake Holder - Mysore Urban Development Authority - MUDA
  1. Upgrading 2 lane outer ring road to 6 lane along with service road from Mysore-Bangalore road to Mysore-Nanjungud road (0 to 25 km-western side ) and upgrading 4 laned outer ring road to 6 lane along with service road from Mysore-Bangalore road to Mysore-Bannur road (0 to 7.49 km Eastern side)
    Appr cost Rs. in Crores - 219.03
     
    • Approved by GOI on 15.02.08 in CSMC meeting. Central and State Govt,.share of Rs. 49.28 crores released vide Govt. order No. UDD 44 CSS 2007 dated 25-3-2008. Tender has been floated on 27-3-2008. Only one agency is qualified in Technical Bid and hence rejected by govt. ,Retender is called for four packages on 17-09-2008. The same Notification has been Questioned in the Honourable High Court Vide W.P No: 13270 of 2008. The Honorable High Court has passed an interim order stating that all further proceedings pursuant to the Notification dated 17-09.2008 will be subject to further order of this court. Further process on Notification is in Progress. Last date for receipt of bids 05/01/09

Pending at GoI

  1. Construction of balance length of the outer ring road with a 6 lane road along with service road from Bannur road to Nanjungud road (Ch. 7.49km to 16.635km)
    Appr cost Rs. in Crores - 90.70
     
    • Final notification for land acquisition completed. Resubmitted to GOI for re-consideration.
       
  2. Development of 35 acres Heritage park in front of Lalith Mahal palace in K.C. Layout, Mysore
    Appr cost Rs. in Crores - 19.00
     
    • Discussed in CSMC meeting on 15.02.08 to be reconsidered after getting comments from heritage experts. Expert committee to be formed by GoI.
 
Stake Holder - BSUB
  1. Rehabilitation of 20 selected slums of Mysore City.(2788 houses)
    17 selected slum rehabilitation
    3 slums development works.
    Project Cost : Rs. 67.58(In Crores)
    • In Phase-I, 1188 houses have been entrusted to Mysore Nirmithi Kendra at a cost of Rs.1.80 Lakhs per dwelling unit and 1170 houses have been entrusted to different empanelled contractors as approved in the SLEC meeting held on 25-10-08. Balance 430 houses decision to construct houses or to provide infrastructure to be decided

      The following works have been started.
      a. Mandakally - 480 Houses
      b. Roopanagar & Bogadi - 144 Houses
      c. Metagally - 276 Houses
      d. Hanchya Sathgally Block 1 - 180 Houses
      e. Hanchya Sathgally Block 2 - 186 Houses
      Total 1266 Houses
  2. Rehabilitation of 46 selected slums of Mysore city(2500 Houses)
    Appr cost Rs. in Crores - 90.93
     
    • As per the SLEC meeting held on 25-10-08,Tenders were finalized and the following pacakges were approved.
      Package II 396 Houses
      Package III - 348 Houses
      Package VII Providng Infrastructure to 5 slums.
      Out of 1244 houses, tenders have been
      called for 1000 houses on 20/12/08 for which land is awaited from Revenue department
 
Stake Holder - Solid Waste Management
  1. Development of an integrated Municipal Solid Waste Management (MSW) plant for the city of Mysore
    Appr cost Rs. in Crores - 28.98
     
    • The Project has been cleared in CSMC meeting held on 19/12/08. Action is taken to Commence IEC activity. Tender documents are being finalised.
 
 
Karnataka State Road Transport Corporation - KSRTC
  1. Infrastructure Development of Transport System in Mysore
    Tendered Cost:Rs. 108.90 crores
    Work awarded on: 25.8.08
    Contract period: 18 months excluding monsoon period (3 months)
    Appr cost Rs. in Crores - 85.25
 
Stake Holder - Heritage Department

Pending at GoI

  1. Conservation of Heritage Buildings.
    Appr cost Rs. in Crores - 2.90
     
  • DPR submitted to GOI. Awaiting approval from GoI.
 
Stake Holder - Tourism Department

Pending at GoI

  1. Development of Tourist Infrastructure In Mysore- Pakage1 development of Chamundi Hill
    Appr cost Rs. in Crores - 13.78
     
    • DPR submitted to GOI. Awaiting approval from GoI.

Pending at GoI

  1. Development of Heritage Core
    Appr cost Rs. in Crores - 51.82
     
    • Awaiting approval from GoI.
 
 
 
     
 
 
Reference Links
 
 Mission Overview

 Jnnurm
      Background


 Brochure

 Annexures

 Whats New

 Programme
       Monitoring and
       Evaluation System

 Compliance Report

 
 Guidelines
  Frame Work & Process
  CDP
  Project Preparation
  Project Appraisal
  Implementing Timeline
 
Reference Sites
 
Govt. of India
 
Govt. of Karnataka
 
Districts of India
 
Right to Information Act (India)
 
 
Mysore City Corporation
 
MUDA Mysore
 
 
Jnnurm WebSite
 
Ministry of Urban Development
 
KUIDFC
 

Ministry of Housing and Urban Poverty Alleviation